Beginning Monday, Dec. 17, the Utilities Department will completely close Holy Cross Drive from west of the Fire Station to east of the St. Liam Parking Lot. This closure is expected to last until Saturday, Jan. 12. The sidewalk between the Fire Station and the St. Liam parking lot will be closed Dec. 3 to Jan. 18. Please see map for details.
This planned closure will give crews time to extensively excavate the road to install new chilled water piping connections as well as other utility connections between the Power Plant and the new Chilled Water Pumping Station. The timing of this road closure coordinates with the holiday break and chilled water system outages so as to minimize impacts to both traffic and system operations.
Originally published by evp.nd.edu on December 06, 2018.